Pittsfield Township closes in on first phase of Platt Road Greenway
Pittsfield Township only needs to acquire three small parcels of land to begin developing the Platt Road Greenway. Township officials hope to get them this summer, put the $350,000 project out to bid later this year and begin construction next spring.
It ‘s a lot like putting together an elaborate puzzle only to discover a couple of key pieces are missing. That’s the case with Pittsfield Township’s efforts to assemble the land for the Platt Road Greenway.
After several years of planning and fundraising the township has acquired all the land needed to build the first phase of the trail. However, it’s missing three small easements to connect it all.
“We’re working on it right now,” says Feliziana Meyer, clerk for
The township is ready to take the parcel by way of imminent domain if the property owners don’t cooperate. However, if everything goes as planned the township expects to put the project out to bid late this year and begin construction next spring.
The 10-foot-wide asphalt trail would run along the east side of
The second phase calls for following Patt from
Source: Feliziana Meyer, clerk for
Writer: Jon Zemke